Production bottleneck: how to find it and expand it without buying equipment

For plants where there are more orders than output. In 2–5 days on site I find what really limits production.

In short

A bottleneck is the area that limits the output of the whole plant. In 2–5 days on site I measure work-centre utilisation, find the bottleneck and give a plan to expand it: first without investment (schedule, changeovers, scrapping defects before the bottleneck), then with investment (equipment, space). The result is a capacity calculation for your product range and a prioritised list of measures.

Book a free consultation

Who it is for

  • More orders, but output does not grow
  • Everyone is busy, yet shipments are late
  • You plan to buy equipment and want to be sure it goes to the right area
  • After the range grew, capacity is «suddenly» not enough

What I do, step by step

  1. 1
    Data and walk-through

    Range, volumes, routings, accounting data; a walk through the site to see where WIP accumulates.

  2. 2
    Utilisation measurement

    Utilisation of work centres by product family, changeovers, downtime, Yamazumi chart for manual operations.

  3. 3
    Bottleneck and capacity

    Where the constraint is and how much the plant can produce with your range.

  4. 4
    Measures without investment

    The five focusing steps of the Theory of Constraints: exploit the bottleneck, subordinate other areas to it, keep defects away from it, cut changeovers, change the schedule.

  5. 5
    Measures with investment

    Only when the no-investment measures are exhausted: equipment, people, space — with a calculated effect.

What you get

  • Capacity calculation for your range
  • Where the bottleneck is and why
  • Prioritised measures: without and with investment
  • Indicators to check the result

What I don't do

  • I do not sell equipment or take supplier commissions
  • I do not promise output growth before measurements

Frequently asked questions

How much does finding the bottleneck cost?

On-site diagnostics — from 2 consultant days (60,000 RUB per day).

What if there are several bottlenecks?

At any moment the constraint is usually one; a «floating» bottleneck is a sign that too much work is released at once. This is visible in the measurements too.

Sources: E. Goldratt, J. Cox, «The Goal»

Tell me what is happening in your production

The first consultation is free: up to 60 minutes online. I reply within one working day; after the call I send written conclusions and suggest a next step — no obligations.

Consultations are held in Russian or English.

Book a free consultation